Every scaffolding project needs proof tests on its tie anchors: under NASC TG4:25, a random sample of at least 1 in 20, with at least 3 in each discrete area, each loaded to 1.25 times the tie duty and the results recorded; TG4:25 notes that tagging each tested anchor with the date and test load is common practice. Where the base material is in doubt, preliminary tests on 5 anchors for each base material, discarded afterwards, come first.
Ο παρών οδηγός εξηγεί πώς σχεδιάζονται και εκτελούνται οι δοκιμές επί τόπου σύμφωνα με τα BS 8539:2012+A1:2021 και NASC TG4:25. Δεν αντικαθιστά τα έγγραφα αυτά, τα στοιχεία του κατασκευαστή των αγκυρίων ή τις οδηγίες του μελετητή, του προδιαγραφέα ή του μηχανικού που είναι υπεύθυνος για το έργο των ικριωμάτων, ο οποίος καθορίζει το πρόγραμμα δοκιμών, τα φορτία και τους συντελεστές. Μια δοκιμή καταγράφει ό,τι συνέβη τη συγκεκριμένη ημέρα· δεν εγκρίνει μια στερέωση για χρήση.
Key figures
| Proof tests | Every project, including anchors already in the building (TG4:25 §9.5) |
|---|---|
| Proof sample | At least 5% (1 in 20), at random, and at least 3 per discrete area (TG4:25 §9.6) |
| Proof load | 1.25 × the tie duty from the TG20 or TG30 compliance sheet or the design |
| Preliminary tests | 5 anchors per base material, to 2 × the tie duty (3 × for nylon unless the maker says otherwise) |
Who is this page for?
Scaffolding contractors, supervisors and designers, and the main contractors who check their paperwork: what applies to tie anchors, the two tests, who does them, the records and the kit.
Which rules and guidance apply to scaffold tie anchors?
| Document | From | What it means for tie anchors |
|---|---|---|
| Work at Height Regulations 2005 | UK legislation | Planning, supervision and competence (regulations 4 and 5). A construction scaffold someone could fall 2 m or more from is inspected within the previous 7 days, and after exceptional circumstances liable to jeopardise its safety (regulation 12) |
| NASC TG4:25 Anchorage Systems for Scaffolding | NASC | Choosing, installing and testing tie anchors. Issued March 2025; a pocket user guide and site poster followed in June 2026 |
| NASC TG20:21 and TG30 | NASC | The tie duty, which test loads are worked out from, comes from their compliance sheets (TG20 for tube and fitting, TG30 for system scaffolds) or a design |
| NASC SG4:22 Preventing Falls in Scaffolding Operations | NASC | Preventing falls during scaffolding work. For fall arrest loads on an anchor, TG4:25 points the scaffold designer to SG4, BS EN 795 and BS 7883 |
| BS 8539:2012+A1:2021 | BSI | Post-installed anchors in concrete and masonry; listed among TG4:25's references |
What tests does a scaffold need?
Preliminary tests answer "will this anchor hold in this wall?" They are for when the base material is in doubt, typically brick, stone or timber that the anchor maker has no data for. Five anchors go in for each base material, away from where the scaffold will be, and are thrown away after the test. Each is loaded to twice the tie duty, or three times for nylon anchors unless the maker states otherwise, and passes if it doesn't slip by 1 mm or more. See preliminary tests.
Proof tests answer "were these anchors put in properly?" They are done on every project, on working anchors chosen at random, and the anchors stay in use. See proof testing and test loads by tie class.
How often are tie anchors checked during the job?
At each statutory scaffold inspection. TG4:25 asks the inspector to look at each tie anchor for deformation, damage, rust running from it, and cracks in the wall or its joints. It also says proof tests may be needed again after severe weather or any undermining of the scaffold, testing anchors not tested before where possible and tagging them.
Under the Work at Height Regulations, the scaffold's inspection report is prepared before the end of the working period and a copy given within 24 hours to the person it was done for. It is kept on site until the construction work is finished, then at an office for 3 months. See checking tie anchors during a long job.
Who may install and test tie anchors?
Competent people only. TG4:25 asks for competent personnel and a gauge calibrated within the last 12 months to an accuracy of 5%, and NASC's own description of TG4:25 gives trained CISRS scaffolders as an example. Under the Work at Height Regulations, everyone involved in work at height, from planning it to doing it, must be competent; the only exception is a trainee working under a competent person's supervision.
What should a scaffold tie test record show?
| For the job | For each anchor tested |
|---|---|
| Site, client and date | Test number and where it is |
| Anchor type and base material | The minimum test load it had to reach |
| Preliminary or proof test | The load it reached, and pass or fail |
How are tested anchors marked?
TG4:25 notes that it is common practice to tag each proof-tested anchor with the date and the test load, and says any that failed should be tagged as such, so nobody uses them. Our free scaffold tie test record and tags template has both, or the Staht Connect app records each test with a photo and a map pin.
Worked example: a 200-tie elevation
A brick elevation has 200 standard duty ties, each with a tie duty of 6.1 kN, all put in by one team.
- Sample. 5% of 200 is 10 anchors, more than the minimum of 3.
- Load. 1.25 × 6.1 kN = 7.625 kN. TG4:25's own table gives 7.6 kN for this tie.
- One failure. The rate rises to 1 in 10 for that area: 20 anchors, more than the minimum of 6.
- Two failures. 1 in 5: 40 anchors, more than the minimum of 12.
- More than two. Every anchor is tested, and the anchor choice and installation are reviewed.
A failure is serious and is investigated, whatever the count.
What kit does a scaffolder need?
A Staht t25 reaches 25 kN, which covers every TG4:25 proof load (4.4, 7.6, 11.4 and 15.3 kN in its table) and preliminary loads up to 24.4 kN for a 12.2 kN tie. Preliminary tests on nylon anchors at three times a 9.1 or 12.2 kN tie are 27.3 and 36.6 kN, beyond a t25: use a t60 for those.
Load the anchor itself through its thread or eye, never through the tie tube. In brickwork, keep the tester's feet off the brick the anchor is in; TG4:25 says the bridge should normally be set vertically to do this. The t25 kit takes threaded and slotted washers from M6 to M16. Hire a t25 for a single job, or buy through Leach's or direct.
Applications and guides for scaffolders
- Scaffold tie testing: the kit
- Scaffold tie anchors and anchor types
- Construction: BS 8539 tests by other trades on the same site
More questions
Yes. TG4:25 asks for proof tests on every project, including anchors installed before. Buildings constructed after 1994 may have anchor points fitted for future maintenance under the CDM Regulations; establish early who is responsible for them and what they can carry, and test them where they may have deteriorated.
No. TG4:25 asks for the load to go straight onto the anchor, not through the tie tube or the fitting.
They may. TG4:25 says proof tests may be needed after severe weather or any undermining of the scaffold, and the Work at Height Regulations ask for an inspection after exceptional circumstances liable to jeopardise the scaffold's safety.
Πηγές
- NASC TG4:25 Anchorage Systems for Scaffolding, NASC
- NASC launches new TG4 update to support anchor tie safety (June 2026), NASC
- TG20:21 Operational Guide, NASC
- SG4:22 Preventing Falls in Scaffolding Operations, NASC
- The Work at Height Regulations 2005, regulation 12: Inspection of work equipment, legislation.gov.uk
- The Work at Height Regulations 2005, regulation 5: Competence, legislation.gov.uk
- The Work at Height Regulations 2005, regulation 4: Organisation and planning, legislation.gov.uk
- BS 8539:2012+A1:2021 Code of practice for the selection and installation of post-installed anchors in concrete and masonry, BSI
Test scaffold ties with the t25
25 kN, M6 to M16, with every test recorded in Staht Connect.