Guide

A kit checklist for an anchor test day

In short

Pack a tester calibrated within the last 12 months with its certificate, a bridge wide enough for the embedment, the right adaptors, a calibrated torque wrench, hole cleaning and setting tools, movement gauges if asked for, fixings to secure the rig, PPE and the test request. Check each item before you leave.

This guide explains how site tests are planned and carried out under BS 8539:2012+A1:2021. It does not replace the standard, the anchor manufacturer's data, or the instructions of the specifier or engineer responsible for the job, who decides the test plan, the loads and the factors. A test records what happened on the day; it does not approve a fixing for use.

Key figures

Calibration of the testerWithin the last 12 months, certificate with you
Blow-out bulbFor holes up to 10 mm in diameter
Brush for resin anchorsHole diameter plus 1 to 2 mm
Thread engagement on couplersAt least 1.5 × the bolt diameter
Dial gauge accuracy, if used0.02 mm or better

What should I check before leaving for a test?

Before leaving, confirm the test plan with whoever asked for the tests. The specifier or responsible engineer decides the plan, so you need from them:

  • From the specifier: the purpose (allowable resistance or proof test, in tension or shear); N_Ek, the test or proof load and the factors behind it; how many anchors there are in all and how many to test in each area; any edge distance to keep.
  • About the anchors: make, type, size, drill diameter, hole depth and installation torque; whether they are already in or you install them.
  • About the site: the base material and its expected strength; access, induction, working at height and parking.

If anything on site differs from the request, such as the base material, ask the person who requested the test before going on. Our test-load calculator checks preliminary test loads.

The checklist

GroupItemNotes
PaperworkTest request and method statementConfirms what to test and to what load
PaperworkTester's calibration certificate, or calibration chartDated within the last 12 months
PaperworkReport forms or the app; for scaffold tie tests, tagsScaffold tie tags: test date and load; failures clearly marked
TestingPull testerCapacity above the highest test load, with the gauge used above 20% of full scale if accurate to ±2% of full scale
TestingBridgeSpacing to suit h_ef; maximum load above the test load
TestingAdaptorsThreaded washers or couplers, slotted washers, clevis, pulling frame and bushes, to suit the anchor
TestingPulling rod, washers and nutsChecked for damage before each test; nuts of a matching grade
TestingSpanners and socketsDeep sockets for projecting studs
InstallingThe anchors to be testedSame make, type and size as specified
InstallingDrill, power supply and drill bitsBits within ISO 5468 medium tolerance; never worn or blunt
InstallingHole cleaning kitWhatever the anchor manufacturer's cleaning procedure needs, reaching the bottom of the hole: typically a blow-out bulb for holes up to 10 mm, a large pump or oil-free compressed air for larger holes, and for resin anchors a brush 1 to 2 mm wider than the hole
InstallingSetting tools for the anchorAs the manufacturer specifies
InstallingCalibrated torque wrenchNever an impact wrench on scaffold tie anchors (NASC TG4:25); otherwise only as the manufacturer allows
Measuring movement, if asked forDial gauge or feeler gaugeDial gauge accurate to 0.02 mm
Measuring movement, if asked forStand with a remote armMounted off the bridge
Securing the rigFixings, drill bits and tethersTo hold the rig on walls and soffits in case the anchor fails
SafetySite PPEAlways: hard hat. Drilling: eye protection; ear defenders for long spells or in a confined space; a dust mask for overhead or enclosed work. Installing overhead: eye protection. Resin: gloves

What comes in a Staht kit?

The Staht t60 kit in a case (a padded-bag version is also sold) comes with the 60 kN load cell and bridge, an anchor jaw, a clevis, threaded washers from M6 to M20, slotted washers from M6 to M16, an anti-rotation arm, a 24 mm ratchet spanner, a 17 mm socket with a 3/8 inch socket wrench, a 6 mm hex key, tool and wrist lanyards, a USB-C cable and a 12-month calibration certificate. See the t60 kit.

The t25 kits cover anchors from M6 to M16 up to 25 kN, with three-legged and four-legged versions. For deeper anchors, add a 375 or 575 bridge and its drop rod. To choose them, see choosing a bridge and connecting the tester to the anchor.

Which extras are worth packing?

Spreader plates, a 3 leg adaptor, leg extensions, threaded adaptors and the shear kit are worth packing when the job needs them:

On site, before the first test

  1. Check the anchors

    Make sure the anchors are the ones specified, and that bonded anchors have cured for at least the recommended time.

  2. Check the base material

    In new construction, make sure it is at least as strong as the specifier assumed.

  3. Check the positions

    Mark each test position, and note any anchor closer to an edge or another anchor than recommended.

  4. Set up the bridge

    Check the support spacing suits the test and the embedment, and that the pull will be straight.

  5. Secure the rig

    On walls and soffits, fix the rig so it cannot fall if the anchor fails.

  6. Keep clear of the line of fire

    Make sure nobody stands directly in front of the tester while it is loaded.

More questions

Sources

  1. BS 8539:2012+A1:2021 Code of practice for the selection and installation of post-installed anchors in concrete and masonry, BSI
  2. NASC TG4:25 Anchorage systems for scaffolding, Sections 8.2, 9.6 and 11.1, NASC
  3. Staht t60 digital pull tester kit product data, Staht

Everything for the test day

Staht's t25 and t60 kits come in a case or bag with their adaptors and a 12-month calibration certificate.

Your basket

Loading your basket…